New Pavilion Photo Timeline
21-02-09: Clubroom walls plastered
29/03/09: New radiator(s) and screeded floor
19/01/09: Phil Cornic of PHS Ltd first fixes the plumbing
21-02-09: Clubroom ceiling plastered
Click on an image to enlarge it
29/03/09: View of clubroom from changing room area
29/03/09: View of clubroom from bar
02/05/09: Accessability ramps in place
02/05/09: Oil drum, generously donated by Fuel Supplies.
02/05/09: New boiler installed
03/06/09: Quality fire doors fitted
03/06/09: Hi-tech security system installed
03/06/09: Alarm system complete & downpipes in